Case Study: Delivering a Multi-Storey Façade System in Record Time
A Race Against Time
Project Overview
| Aspect | Details |
|---|---|
| Client | Leading Colombo-based real estate developer |
| Project Type | Commercial multi-storey building |
| Scope | Commercial multi-storey building |
| Timeline | 6 months (typical project of this scale requires 9–12 months) |
| Key Challenges | Tight schedule, material logistics, monsoon season disruptions |
| Unisyst’s Role | End-to-end solution provider under the Hayleys Group banner |
Challenge: Beating the Clock Without Compromising Quality
Key hurdles included:
- Compressed project timeline compared to industry standards.
- Supply chain disruptions for aluminium systems.
- Weather challenges during monsoon season in Sri Lanka.
- High-rise safety concerns for multi-level façade installation.
Our Solution: Combining Expertise and Innovation
Advanced Design & Engineering
a. Used BIM (Building Information Modelling) to simulate façade design, clash detection, and installation sequencing.
b. Optimised panel sizes and framing systems to reduce fabrication complexity.
c. Ensured compliance with Sri Lankan building codes and international standards.
Streamlined Fabrication Process
a. Leveraged in-house facilities to fabricate custom aluminium profiles and panels.
b. Adopted Just-In-Time (JIT) manufacturing to align with site requirements.
c. Implemented quality assurance at each stage, minimizing rework.
Agile Project Management
a. Coordinated across stakeholders (architects, engineers, contractors) via weekly virtual check-ins.
b. Applied modular installation techniques, enabling faster on-site assembly.
c. Built contingency buffers into the schedule to handle monsoon interruptions.
| Phase | Traditional Timeline | Unisyst Timeline |
|---|---|---|
| Design & Engineering | 3 months | 2 months |
| Fabrication & QA | 4–5 months | 3 months |
| On-site Installation | 3–4 months | 1 month |
| Total Duration | 10–12 months | 6 months |
Results: More Than Just On-Time Delivery
- On-Time Completion: Delivered in 6 months, meeting the client’s grand opening target.
- Cost Savings: Optimised resource use saved approximately 15% in project costs.
- Safety Excellence: Zero incidents reported during the high-rise installation phase.
- Enhanced Aesthetics: A sleek, modern façade reinforced the building’s premium positioning.
Why This Case Matters for Future Projects
Key Takeaways for Developers and Architects
- Plan with BIM early: Reduces redesigns and saves weeks in the timeline.
- Choose contractors with in-house fabrication: Ensures speed and quality control.
- Integrate project management digitally: Keeps all stakeholders aligned.
- Think modular: Prefabrication is the future of aluminium façades.